Current Dev Position: YP 2.3 M1
Next Deadline: YP 2.3 M1 by Dec. 12, 2016
SWAT team rotation: Leo -> Juro
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Key Status/Updates:
* 2.1.2 QA report is out and likely to be released imminently.
* The QA report for 2.1.2 is at: https://wiki.yoctoproject.org/wiki/WW46_-_2016-11-10_-_Test_Cycle_2.1.2_rc1
* At this point most 2.3 targeted features should have been identified in bugzilla. M1 is comparatively loaded compared to M2/M3 and some individuals have particularly heavy workloads so loading balancing is being done.
* We'll run a 2.0.3 test build over the weekend to find out our status there.
* Backports of fixes to the morty release branch are now occurring, thanks Armin. Armin is looking like the principle morty maintainer for that stable release series.
* There are some changes planned to the getVar/getVarFlag expansion defaults and the old data store APIs are likely to be removed imminently. There is an email on the openembedded-architecture list about this.
* WDD is now climbing again unfortunately, we've wiped out half of the improvements we made in the 2.2 cycle.
Proposed upcoming dot releases:
YP 2.0.3 Release by Dec. 9, 2016
YP 2.2.1 Release by Jan. 20, 2017
YP 2.1.3 Release by May. 19, 2017
Key YP 2.3 Dates:
YP 2.3 M1 Cutoff is Dec. 12, 2016
YP 2.3 M1 Release is Dec. 23, 2016
YP 2.3 M2 Cutoff is Jan. 23, 2017
YP 2.3 M2 Release is Feb. 3, 2017
YP 2.3 M3 Cutoff is Feb 27, 2017
YP 2.3 M3 Release is Mar. 10, 2017
YP 2.3 M4 Cutoff is April 3, 2017
YP 2.3 M4 Release is April 28, 2017
Tracking Metrics:
WDD 2516 (last week 2497)
(https://wiki.yoctoproject.org/charts/combo.html)
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.3_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.3_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.3_Features
[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
* Work Telephone: (503) 712-0534
* Cell: (208) 244-4460
* Email: stephen.k.jolley at intel.com
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.openembedded.org/pipermail/openembedded-core/attachments/20161118/d299914c/attachment-0002.html>
More information about the Openembedded-core
mailing list