[OE-core] Yocto Project Status WW07’17

Jolley, Stephen K stephen.k.jolley at intel.com
Mon Feb 13 18:22:49 UTC 2017


Current Dev Position: YP 2.3 M3

Next Deadline: YP 2.3 M3 by Feb. 27, 2017


SWAT team rotation: Leo-> Juro on Feb. 10, 2017.

SWAT team rotation: Juro -> Anibal on Feb. 17, 2017.

https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

·        YP 2.3 M2 was rebuilt and this time the oeqa tests worked. The Recipe Specific Sysroots (RSS) work had a number of key bugfixes and performance also improved significantly.

·        The QA reports for M2-rc3 is https://wiki.yoctoproject.org/wiki/WW06_-_2017-02-03_-_Full_Test_Cycle_2.3_M2_rc3 and this will likely be released in the next day or two.

·        Some rootfs construction phase tests are still being investigated for performance issues.

·        YP 2.2.1 is now in QA after a successful build.

·        Patch merging continues to be steady. ELC (and travel for it) may distract people and continue to impact patch merging progress amongst other things.

·        Due to commitments/conflicts of several contributors, we’ve taken the decision to move the final 2.3 release date out by a week to avoid scheduling issues. This effectively lengthens M4 by a week, M3 remains unchanged and hopefully won’t adversely affect anyone.


Proposed upcoming dot releases:

YP 2.2.1 Release by Feb. 24, 2017

YP 2.1.3 Cut off May 8, 2017

YP 2.1.3 Release by May 19, 2017

YP 2.2.2 Cut off May 22, 2017

YP 2.2.2 Release by June 2, 2017


Key YP 2.3 Dates:

YP 2.3 M3 Cutoff is Feb 27, 2017

YP 2.3 M3 Release is Mar. 10, 2017

YP 2.3 M4 Cutoff is April 10, 2017

YP 2.3 M4 Release is May 5,  2017


Tracking Metrics:

            WDD 2683 (last week 2667)

(https://wiki.yoctoproject.org/charts/combo.html)


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.3_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.3_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.3_Features

[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
•   Work Telephone:        (503) 712-0534
•    Cell:               (208) 244-4460
• Email:                            stephen.k.jolley at intel.com

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.openembedded.org/pipermail/openembedded-core/attachments/20170213/3305e9dc/attachment-0002.html>


More information about the Openembedded-core mailing list