[OE-core] Yocto Project Status WW09’17
akuster808
akuster808 at gmail.com
Tue Feb 28 02:09:37 UTC 2017
On 02/27/2017 08:59 AM, Jolley, Stephen K wrote:
>
> Current Dev Position: YP 2.3 M3
>
> Next Deadline: YP 2.3 M3 by Feb. 27, 2017
>
> *** FEATURE FREEZE for 2.3 is now in effect. ***
>
> SWAT team rotation: Anibal -> Todor on Feb. 24, 2017.
>
> SWAT team rotation: Todor -> Tracy on Mar. 4, 2017.
>
> https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
>
> Key Status/Updates:
>
> ·We’re now into feature freeze for 2.3.
>
> ·We need to decide which recently submitted items should be merged.
> Some major items In particular:
>
> orpm v4/dnf to replace rpm v5/smart?
>
IMHO, we should include dnf in 2.3 so folks can start playing with it
and remove smart in 2.4.
> oMerging go into OE-Core?
>
> oSeparate out elderly GPLv2 into a separate layer?
>
yes, but maybe not for 2.3 if its a large effort.
> oGraphics stack vulkan changes?
>
The "Go" changes hit before the vulkan. Both should have the same rules
applied which ever way the decision goes.
> oLarge queue of wic changes?
>
> I am leaning towards trying to take these even if they do delay the M3
> release slightly as we do have some time left in M4 to stabilize.
>
> ·Unfortunately we continue to have stability issues in testing. There
> appear to be some intermittent failures which have crept into master
> and M3 merging will likely be delayed until those issues have been
> tracked down. They seem to affect sdk image size, breaking the 4GB
> limit and eSDKs stopping containing libxml2 under unknown
> circumstances, possibly amongst other issues.
>
> ·YP 2.2.1 has been released
>
thanks to all that help.
> Proposed upcoming dot releases:
>
> YP 2.1.3 Cut off May 15, 2017
>
> YP 2.1.3 Release by May 26, 2017
>
> YP 2.2.2 Cut off May 29, 2017
>
> YP 2.2.2 Release by June 9, 2017
>
I like the dot release schedule. Helps me focus.
kind regards,
Armin
>
> Key YP 2.3 Dates:
>
> YP 2.3 M3 Cutoff is Feb 27, 2017
>
> YP 2.3 M3 Release is Mar. 10, 2017
>
> YP 2.3 M4 Cutoff is April 10, 2017
>
> YP 2.3 M4 Release is May 5, 2017
>
> Tracking Metrics:
>
> WDD 2747 (last week 2682)
>
> (https://wiki.yoctoproject.org/charts/combo.html)
>
> Key Status Links for YP:
>
> https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.3_Status
>
> https://wiki.yoctoproject.org/wiki/Yocto_2.3_Schedule
>
> https://wiki.yoctoproject.org/wiki/Yocto_2.3_Features
>
>
> [If anyone has suggestions for other information you’d like to see on
> this weekly status update, let us know!]
>
> Thanks,
>
> */Stephen K. Jolley/**//*
>
> *Yocto Project Program Manager*
>
> *INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124 *
>
> (*Work Telephone*: (503) 712-0534
>
> (*Cell*: (208) 244-4460
>
> * *Email*:_stephen.k.jolley at intel.com_
>
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.openembedded.org/pipermail/openembedded-core/attachments/20170227/25531851/attachment-0002.html>
More information about the Openembedded-core
mailing list